A manufacturing company uses three processes to make its two products, X and Y. The time available on the three processes is reduced because of the need for preventative maintenance and rest breaks.
The table below details the process times per product and daily time available:
Process Hours available Hours required to make Hours required to make
per day one unit of product X one unit of product Y
1 22 1.00 0.75
2 22 0.75 1.00
3 18 1.00 0.50
Daily demand for product X and product Y is 10 units and 16 units respectively.
Which of the following will improve throughput?