筛选结果 共找出469
材料全屏
60

【单项选择题】

What was the adverse material price variance?

A

$1,000

B

$3,500

C

$7,500

D

$11,000

What was the favourable material usage variance?

A

$2,500

B

$4,000

C

$7,500

D

$10,000

材料全屏
62

【单项选择题】

What was the total direct materials variance?

A

Nil

B

$10,000 Adverse

C

$10,000 Favourable

D

$11,000 Adverse

What was the total direct labour variance?

A

$6,000 Favourable

B

$20,000 Adverse

C

$22,000 Favourable

D

Nil

What was the total direct variable overheads variance?

A

Nil

B

$12,000 Favourable

C

$12,000 Adverse

D

$11,000 Adverse

材料全屏
65

【单项选择题】

What was the actual production in February?

A

200 units

B

217 units

C

240 units

D

280 units

材料全屏
83

【单项选择题】

Raw material opening inventories are budgeted as follows.

                                              April                              May                                 June

                                            3,800 kg                        4,200 kg                           4,100 kg

The closing inventory budgeted for June is 3,900 kg.

Material purchases are paid for in the month following purchase. What is the figure to be included in the cash budget for June in respect of payments for purchases?

A

$25,100

B

$48,800

C

$50,200

D

$50,600

Wages are paid 75% in the month of production and 25% in the following month. be included in the cash budget for May in respect of wages? 

A

$222,600

B

$231,000

C

$233,800

D

$235,200

材料全屏
85

【单项选择题】

What is the non-discounted payback period of Project Beta?

A

2 years and 2 months

B

2 years and 4 months

C

2 years and 5 months

D

2 years and 6 months

What is the discounted payback period of Project Alpha?

A

Between 1 and 2 years

B

Between 3 and 4 years

C

Between 4 and 5 years

D