【单项选择题】
What was the adverse material price variance?
What was the favourable material usage variance?
【单项选择题】
What was the total direct materials variance?
What was the total direct labour variance?
What was the total direct variable overheads variance?
【单项选择题】
What was the actual production in February?
【单项选择题】
Raw material opening inventories are budgeted as follows.
April May June
3,800 kg 4,200 kg 4,100 kg
The closing inventory budgeted for June is 3,900 kg.
Material purchases are paid for in the month following purchase. What is the figure to be included in the cash budget for June in respect of payments for purchases?
Wages are paid 75% in the month of production and 25% in the following month. be included in the cash budget for May in respect of wages?
【单项选择题】
What is the non-discounted payback period of Project Beta?
What is the discounted payback period of Project Alpha?